The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare and plan to commission/decommission gas transmission pipelines
|
|
Work schedule(s), including drawings, plans, requirements, established procedures and material lists are received, analysed and confirmed if necessary by site inspection Completed |
Evidence:
|
WHS/OHS and environmental measures for the sites are identified, obtained and understood. Completed |
Evidence:
|
Relevant requirements and established procedures for the work are communicated to all persons and identified for all work sites Completed |
Evidence:
|
WHS/OHS, environmental and sustainable energy policies and procedures are obtained and confirmed and communicated Completed |
Evidence:
|
Work is prioritised and sequenced by management following consultation with others for completion within acceptable timeframes and in accordance with established procedures Completed |
Evidence:
|
Hazards are identified, WHS/OHS risks are assessed and control measures are prioritised, implemented and monitored against the work schedule and established procedures. Completed |
Evidence:
|
Relevant work permits are obtained to access, isolate/de-energise systems and perform work according to requirements and established procedures Completed |
Evidence:
|
Scope of responsibility under the relevant work permit/authorization is received and confirmed with relevant persons according to requirements and established procedures Completed |
Evidence:
|
Resources including persons, equipment, tools, materials, plans, specifications and personal protective equipment required to carry out the work are identified, scheduled and obtained and checked for operation and safety Completed |
Evidence:
|
Relevant persons at worksite are confirmed to be current in First Aid and other related work procedures according to requirements Completed |
Evidence:
|
Liaison and communication issues with authorised persons, authorities, clients and land owners are resolved and activities coordinated to carry out work by management Completed |
Evidence:
|
Pipeline in check for readiness (cleaned, pigged, bypassed, etc.) for commissioning/ decommissioning Completed |
Evidence:
|
Site is prepared according to the work schedule and to minimise risk and damage to property, commerce and individuals in accordance with established procedures Completed |
Evidence:
|
Persons participating in the work, including plant operators and contractors are fully briefed and respective responsibilities confirmed in accordance with established procedures Completed |
Evidence:
|
Road signs, barriers and warning devices are positioned in accordance with requirements including traffic management plans Completed |
Evidence:
|
Commission/decommission gas transmission pipelines
|
|
WHS risk control measures, schedule of work and standard operating procedures for carrying out the work are followed Completed |
Evidence:
|
Appropriate materials, tools, equipment and measuring devices are selected and used correctly and safely. Completed |
Evidence:
|
Hazardous activities such as lifting, climbing, working in confined spaces, excavations, trenches, or aloft, and use of power tools, techniques and practices are conducted safely accordance with given instructions and requirements Completed |
Evidence:
|
Commissioning/ decommissioning of gas transmission pipelines is carried out efficiently in an agreed timeframe and to required standards with a minimum of waste of materials or damage to apparatus, circuits, the surrounding environment or services and using sustainable energy principles Completed |
Evidence:
|
Commissioning/decommissioning of gas transmission pipelines is carried out in accordance with the work schedule and to requirements/established procedures Completed |
Evidence:
|
Hazard warnings and safety signs are recognised and hazards are assessed and WHS/OHS risks and incidents are reported to the immediate authorised persons for directions according to established procedures Completed |
Evidence:
|
Adjustments are made for unplanned events in commissioning/decommissioning of gas transmission pipelines are undertaken within the scope of established procedures Completed |
Evidence:
|
Procedures for referring non-routine events to the immediate authorised persons for directions are followed Completed |
Evidence:
|
Reports and ongoing checks of quality of the work are undertaken in accordance with given instructions and established procedures Completed |
Evidence:
|
Complete work and relevant documentation
|
|
WHS/OHS risk control work completion measures and procedures are followed Completed |
Evidence:
|
Tools and equipment appropriate to the testing requirements are selected and work undertaken is checked against works schedule for conformance with requirements, anomalies are reported in accordance with established procedures
|
|
Accidents and injuries are reported in accordance with requirements and established procedures where applicable Completed |
Evidence:
|
Work site is rehabilitated, cleaned up and made safe in accordance with given instructions and established procedures Completed |
Evidence:
|
Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and stored securely in accordance with established procedures Completed |
Evidence:
|
Relevant work permit(s) are signed off and equipment is returned to service in accordance with requirements Completed |
Evidence:
|
Final inspections are undertaken and work completion documentation is finalised and processed accurately and provided to appropriate persons in accordance with established procedures. Completed |
Evidence:
|